Biogas Delivery System and OEF150 Flare Project
Equipment overview:
The by-product from the processing plant and waste water, are directed to Covered Anaerobic Ponds (CALs) and from here biogas is captured and used as an alternative fuel source to co-fire the boiler to produce steam for the plant.
Energy360 worked in close collaboration with the project engineers, to design a system of pipework which would effectively deliver the biogas to the boiler.
Key elements of the projects produced by Energy360:
Contact us for more information: Contact Energy360
Biogas Upgrading:
Energy360 can upgrade the biogas generated by using world leading biogas to biomethane upgrading technology.
The upgraded biomethane can then be injected to the grid, which enables customers to utilise the valuable, onsite biogas to generate an income stream and offset the profit impact of natural gas price increases without risk to the site’s processing operations.
- Biogas delivery system including a PDA blower, methane analysers, pressure transmitters, CAL control valves, and water seals to control CAL pressure.
- Energy360 specialist OEF 150 flare with high reliability, high turn down, fast response and good destructive efficiency.
- The boiler which was modified to accept biogas, is now co-firing using the biogas and annual energy costs have fallen significantly
- The plant’s carbon emmisions have also been reduced substantially